Concepts

Positive risk refers to the potential benefits or opportunities that may arise from uncertain situations or conditions. They are not perceived as threats but as possibilities that could favorably impact the project if capitalized upon proactively. Unlike negative risks, positive risks provide project managers an opportunity to elevate a project’s performance and accordingly enhance results.

For example, finding a certain construction material at a cost significantly lower than budgeted would be a positive risk. It would not only save on the procurement cost but could also shorten the project timeline if the materials are readily available.

II. Steps to Manage Positive Risk

A. Risk Identification

The first step towards managing positive risks is to identify them. This involves routinely scanning the project environment for potential opportunities that can enhance the project’s performance.

B. Risk Analysis

Once identified, each positive risk should then be analyzed for its potential impact and the probability of the opportunity occurring. This process helps prioritize the opportunities that will be planned for and acted upon.

C. Risk Response Strategy

After analyzing the positive risks, project managers must then formulate appropriate risk response strategies. A common strategy used for managing positive risk is ‘exploitation,’ aimed at increasing the likelihood of a positive risk to maximize its beneficial impact.

D. Monitor and Control Risks

Regular monitoring and control help ensure that the associated procedures for delivering the benefit are working effectively and that the risk has been fully realized.

III. Positive Risks impact on Project Outcomes

The appropriate management of positive risks can significantly improve project outcomes, including:

  • Enhanced Project Performance: By leveraging potential opportunities, the overall performance of the project can be improved.
  • Decreased Project Duration: Positive risks may enable an acceleration in project schedules, shortening the duration.
  • Cost-efficiency: Positive risks like cost savings could result in lowering a project’s costs.
  • Stakeholder Satisfaction: The realization of positive risks often leads to increased stakeholder satisfaction.

IV. Embrace Positive Risk in Construction Projects

It’s crucial for professionals preparing for the PMI-CP exam to understand that shifting the team’s mindset from risk aversion to embracing the opportunities that positive risks can bring about a transformative project outcome. Consequently, learning to identify, analyze, respond, and monitor positive risk becomes a quintessential skill set for project management professionals.

For instance, an unexpected availability of a more advanced construction material could pose a positive risk. Instead of avoiding it due to unfamiliarity, project managers who are able to effectively exploit this situation, could not only improve the project’s quality but also enhance stakeholder satisfaction.

In conclusion, understanding positive risks is not an option but a necessity for project managers and professionals appearing for the PMI-CP exam. Recognizing the potential of these risks and exploiting them effectively can elevate project outcomes to new heights.

Answer the Questions in Comment Section

True or False: A positive risk is undesirable for a project.

  • Answer: False

Explanation: Positive risks are advantageous to the project as they can offer an opportunity for improvement or advancement.

Which of the following are methods to use positive risk to improve project outcomes?

  • a) Neglecting the risk
  • b) Exploiting the risk
  • c) Sharing the risk
  • d) Accepting the risk without any plan

Answer: b) Exploiting the risk and c) Sharing the risk

Explanation: Exploiting and sharing the risk are positive strategies for dealing with risks that have the potential to improve project results.

True or False: Exploiting a risk means ensuring that the opportunity is realized.

  • Answer: True

Explanation: Exploiting the risk in project management means making the necessary adjustments to ensure the opportunity is realized.

Which of the following could be considered as a positive risk in a construction project?

  • a) Overspending on materials
  • b) The project being delayed
  • c) An expert laborer joining the team unexpectedly
  • d) Equipment breakdown

Answer: c) An expert laborer joining the team unexpectedly

Explanation: An expert worker joining the team unexpectedly could expedite tasks and improve workmanship, which can lead to better project outcomes.

Positive risks are always beneficial for project outcomes?

  • Answer: False

Explanation: Positive risks provide opportunities, but they are still risks, and there is no guarantee they’ll lead to beneficial outcomes. Proper management of these risks is key.

Which of these project risk responses would you primarily use with positive risks?

  • a) Mitigate
  • b) Transfer
  • c) Exploit
  • d) Avoid

Answer: c) Exploit

Explanation: Exploitation, in terms of risk management, is about allocating resources to ensure that potential opportunities are realized.

True or False: You can quantify the impact of positive risks.

  • Answer: True

Explanation: Just like negative risks, positive risks could also be quantified in order to better understand the potential opportunities they could provide or the harm they could inflict on the project.

Can sharing positive risk improve project outcomes?

  • a) Yes
  • b) No

Answer: a) Yes

Explanation: Sharing involves partnering with another party to pursue the opportunity, thus spreading both the responsibility and benefit.

The positive risk of a construction project being completed early would lead to:

  • a) Increased stakeholder pressure
  • b) Reduced project cost
  • c) Increased project scope
  • d) Health and safety concerns

Answer: b) Reduced project cost

Explanation: If a project is completed early, it could lead to reduced labor, utility, and equipment costs.

True or False: Risk management only involves identifying negative risks to a project.

  • Answer: False

Explanation: Risk management includes identifying and managing both positive and negative risks to optimize project outcomes.

Which is a proper positive risk response strategy for a construction project?

  • a) Threat assessment
  • b) Risk mitigation
  • c) Risk enhancement
  • d) Resistance planning

Answer: c) Risk enhancement

Explanation: Risk enhancement, similar to risk exploitation, involves increasing the exposure to a risk so that a project could take full advantage of the opportunity.

True or False: Effective positive risk management can reduce project uncertainty?

  • Answer: True

Explanation: By identifying and managing positive risks proactively, a project leader can reduce uncertainty and enhance the likelihood of project success.

0 0 votes
Article Rating
Subscribe
Notify of
guest
23 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Ümit Akyürek
6 months ago

Great blog post! Recognizing positive risk can really turn a potential issue into an advantage.

Nicoline Nielsen
7 months ago

I appreciate the detailed strategies given for identifying positive risks in construction projects.

Gary Richards
4 months ago

How can we differentiate between a positive risk and an opportunity?

Lorenzo Thomas
6 months ago

Thanks for sharing! This post really helps to understand the concept of positive risks.

Vlast Bosik
7 months ago

Does anyone have an example of a positive risk in a construction project they’ve worked on?

Jozef Veltmaat
7 months ago

This is a fascinating topic. I think more construction managers need to be aware of positive risks.

Hasan Neumaier
7 months ago

The best way to identify positive risks is during risk assessment workshops. Anyone else agree?