Concepts

In the field of construction project management, understanding contractual clauses is fundamental to achieving successful project delivery outcomes. When studying for the PMI-CP examination, students are exposed to various substantial contractual clauses embedded within Built Environment Contracts (BEC) that can significantly impact project delivery. This article aims to discuss some of these pivotal clauses, providing examples to illustrate their implications.

1. Scope of Work Clauses:

The Scope of Work is probably the most crucial clause in a contract, outlining exactly what work will be done under the contract’s terms. This clause contains the description of the services the contractor will provide, including design plans, materials, labor, and the final outcome. An accurately defined Scope of Work can prevent misunderstandings and disputes.

Example: A contract might specify the construction of a two-story office building, listing out components like the type of windows, the color of paint, and even the specific brand of light fixtures that will be installed.

2. Payment Terms:

The contract must clearly dictate when and how the contractor and subcontractors will be paid. This section should detail the amount of the initial down payment, the subsequent payments, and the final payment due upon completion of the project.

Example: A payment schedule in a contract may include 20% upfront, 30% upon completion of the foundation, 30% when the building is ‘watertight’, and the remaining 20% when the project has been completed and signed off by the building inspector.

3. Change Order Clauses:

A change order clause allows alterations in the scope of work after a project has begun. It serves to protect both the owner and the contractors, ensuring additional work is paid for and reducing potential conflict.

Example: If the owner decides they want an additional room added while the construction is ongoing, the change order clause will guard the contractor, ensuring they receive payment for this extra work.

4. Delay Clauses:

This clause protects all parties involved when there are unavoidable delays in the project. It explains the conditions under which an extension of time can be considered, which protects the contractor from having to pay penalties for late completion.

Example: If there is a delay in the delivery of essential building materials due to a supplier’s mistake, the delay clause can allow the completion date to be moved, not penalize the contractor.

5. Termination Clauses:

There should also be provisions in the contract for when either party can terminate the agreement. Situations may arise where a contractor fails to deliver on their obligations, or a client fails to pay for the services provided.

Example: If a client defaults on payment for more than 60 days, a termination clause could allow the contractor to halt services and determine the contract as ended.

6. Dispute Resolution Clauses:

In the unfortunate event of disagreements, dispute resolution clauses provide a mechanism to manage conflicts. This could range from negotiation and mediation to arbitration or litigation.

Example: A dispute resolution clause could stipulate that both parties will seek to resolve any disputes through mediation firstly, then proceed to formal litigation if a resolution is not found.

Conclusion

In conclusion, by grasping these essential clauses and how they work within the built environment contracts, aspiring project managers can manage project risks better and ensure successful project delivery. Remember, a well-prepared contract aligns the expectations of all parties involved, ensuring smoother implementation of the project, reduction of conflicts, and most importantly, the delivery of desired project outcomes.

Consider these key contractual clauses as pillars to your PMI-CP exam preparation and your future professional endeavors in project delivery.

Answer the Questions in Comment Section

In the built environment contracts, project schemas must be included.

  • 1) True
  • 2) False

Answer: True

Explanation: Project schemes provide a detailed overview of the project’s timeline, budget, and targets. They are an essential part of built environment contracts.

Which of the following is not an important clause in built environment contracts?

  • 1) Payment clause
  • 2) Termination clause
  • 3) Time clause
  • 4) Dissolution clause

Answer: Dissolution clause

Explanation: Generally, dissolution clause is not an important clause in building environment contracts, as they are related to partnership contracts, not construction contracts.

Damages for delay clause in built environment contracts provides for a sum to be paid to the owner by the contractor for every day beyond the completion date.

  • 1) True
  • 2) False

Answer: True

Explanation: A Damages for Delay clause, also known as liquidated damages clause, ensures the contractor completes the project by the agreed completion date or compensates the owner for each day of delay.

Qualification based selection of consultants is not commonly used in project delivery.

  • 1) True
  • 2) False

Answer: False

Explanation: Qualification based selection is commonly used in project delivery to ensure consultants are chosen based on their skills and experience.

A termination clause in construction contracts always favours the project owner.

  • 1) True
  • 2) False

Answer: False

Explanation: Termination clauses are designed to protect both parties – they allow both the owner and the contractor to terminate the contract under specific circumstances.

The Scope of Work clause provides details about payment timeline in a construction contract.

  • 1) True
  • 2) False

Answer: False

Explanation: The Scope of Work clause refers to the specific tasks that the contractor will perform, not the payment timeline.

Which of the following is not commonly a part of the built environment contract clauses?

  • 1) Site Investigation clause
  • 2) Quality Control clause
  • 3) Taxation clause
  • 4) Fast Food clause

Answer: Fast Food clause

Explanation: The Fast Food clause is not related to construction contracts. It does not apply in this context.

A clause for dispute resolution is not necessary in built environment contracts for project management.

  • 1) True
  • 2) False

Answer: False

Explanation: Dispute resolution clauses are essential in project management contracts to offer guidance on how disagreements should be addressed and resolved.

The ‘Force Majeure’ clause provides for unforeseeable circumstances that prevent someone from fulfilling a contract.

  • 1) True
  • 2) False

Answer: True

Explanation: A Force Majeure clause frees both parties from contractual obligations when circumstances beyond their control, such as natural disasters, make the contract impossible to fulfill.

‘Retainage’ clause in a construction contract stipulates that a certain amount of the contract price is withheld until the contractor has fully performed.

  • 1) True
  • 2) False

Answer: True

Explanation: The Retainage clause provides a guarantee against the final product being unsatisfactory or the project not being completed. It offers the client some financial security.

The ‘Suspension of Work’ clause in a contract permits the project owner to temporarily halt the project.

  • 1) True
  • 2) False

Answer: True

Explanation: A Suspension of Work clause offers protection to both the project owner and the contractor by allowing the project to be put on hold under certain agreed circumstances.

The ‘Lien Waiver’ clause is used to relinquish the right to claim a lien against the property being improved.

  • 1) True
  • 2) False

Answer: True

Explanation: A lien waiver clause is an important protection for property owners, ensuring contractors can’t claim a lien against the property once they have been paid for their work.

0 0 votes
Article Rating
Subscribe
Notify of
guest
22 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Anna Jørgensen
8 months ago

Great blog post! The discussion on built environment contracts was really insightful.

Gafiya Kozhuhar
7 months ago

The importance of the Force Majeure clause cannot be overstated. It really helps mitigate unforeseen risks.

Mandy Ritz
7 months ago

Well-explained post! I think the Termination clause should also be given attention. It’s a crucial safety net for both parties.

Insa Ostermeier
7 months ago

Thanks for sharing this. Helped me understand the role of contract clauses better.

Cecilie Rasmussen
7 months ago

Can anyone provide more details on the Liquidated Damages clause?

Graciela Véliz
7 months ago

Found the explanation of the indemnity clause very comprehensive. Thanks!

Chris Burton
8 months ago

Change Order clauses are equally important, especially in large scale projects where scope changes are common.

Anka Kapetanović
6 months ago

Dispute Resolution clauses save a lot of headache down the line. Mediation and arbitration can be less adversarial than court cases.

22
0
Would love your thoughts, please comment.x
()
x