Concepts

Sprint Planning is an essential event in the Scrum framework where the team decides the product backlog items to focus on for that sprint and discusses their initial plan for completing those items. For those preparing for the Certified ScrumMaster (CSM) exam, gaining an in-depth understanding of this process is critical.

Understanding Sprint Planning

Scrum defines Sprint Planning as a time-boxed meeting that kick-starts the Sprint. It establishes a vital foundation for a successful sprint by facilitating a shared understanding among the Scrum team regarding the objective and scope for the upcoming sprint. Here are some key considerations:

  • Duration: Sprint Planning meetings typically last about 2 hours for a 2-week Sprint and 4 hours for a 4-week Sprint.
  • Participation: The Scrum Team, including the Product Owner, Scrum Master, and Development Team, takes part in this event.
  • Output: The output of Sprint Planning is a Sprint Goal and a Sprint Backlog. The Sprint Backlog consists of a selected set of Product Backlog items and an adaptive strategy to deliver them.

Key Elements in Sprint Planning

1. Sprint Goal: The Sprint Goal is an objective for the Sprint that can be met through the realization of Product Backlog items and gives guidance to the Development Team on why it is building the increment.
2. Sprint backlog: The Sprint Backlog comprises the Product Backlog items chosen for the Sprint and a plan for implementing those items.
3. Capacity: The team’s capacity is a critical factor to consider in Sprint Planning. This figure can be derived by multiplying the number of team members by the number of working days in a sprint, and then multiply that number by the available hours per team member.

Example:

If we have a 5-member team with a 2-week sprint (10 working days) and each member is available for 6 hours per day, then the total capacity for that sprint would be 5 members X 10 days X 6 hours = 300 hours.

Number of Team Members 5
Sprint Duration (In Working Days) 10
Available Hours per Member per Day 6

Capacity = 5 X 10 X 6 = 300 Hours

Steps for a Successful Sprint Planning

  1. Review and Update the Product Backlog: The Product Owner presents the highest priority items in the Product Backlog to the team.
  2. Estimate Sprint Backlog Items: The Development Team, with the guidance of the Product Owner and Scrum Master, estimates how much work can be completed during the sprint, considering the team’s capacity.
  3. Determine Sprint Goal: The Scrum Team discusses and establishes a Sprint Goal that guides the team.
  4. Create a Sprint Backlog: The Development Team selects Product Backlog items aligned with the Sprint Goal to include in the Sprint Backlog and plans how they will work on the selected items.
  5. Craft a Plan for the Sprint: The Development Team designs a plan to achieve the Sprint Goal and deliver the desired increment.

In conclusion, Sprint Planning plays an essential role in fostering team collaboration and setting a defined direction for the Sprint, making it a crucial event to understand for the Certified ScrumMaster (CSM) exam. A solid grasp of its purpose, sequencing, and those involved sets you up for success, both in your certification and in the Scrum field.

Answer the Questions in Comment Section

True or False: The purpose of Sprint Planning is to determine what can be delivered in the forthcoming sprint.

  • True
  • False

True

In Sprint Planning, the entire team collaborates on understanding the work for the next sprint. Who usually facilitates this meeting?

  • Product owner
  • Scrum Master
  • Stakeholder
  • Development Team

Scrum Master

True or False: A Sprint Planning meeting is time-boxed to a maximum of 8 hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

  • True
  • False

True

What are the crucial outputs of a Sprint Planning meeting? (Multiple Select)

  • Sprint Goal
  • Sprint Backlog
  • Definition of Done
  • Product Backlog

Sprint Goal, Sprint Backlog

True or False: The Product Owner can make changes to the Sprint Backlog during the Sprint.

  • True
  • False

False

During Sprint Planning, the development team should agree on a Sprint goal. This goal is a(n)

  • Executive summary of the Project Charter
  • Broad objective for the sprint that aligns with the product owner’s expectations
  • Detailed task list that must be achieved during the sprint
  • Description of the features that the product needs

Broad objective for the sprint that aligns with the product owner’s expectations

True or False: Team members are not allowed to ask questions or request further details on user stories during the Sprint Planning meeting.

  • True
  • False

False

Who is responsible for ensuring that the development team understands the goals, scope, and product domain during the Sprint Planning?

  • Scrum Master
  • Product Owner
  • Development Team
  • Stakeholder

Product Owner

The Sprint Backlog is primarily comprised of

  • Unresolved product backlog items
  • The product backlog items selected for the sprint
  • All product backlog items
  • Tasks left incomplete from the previous sprint

The product backlog items selected for the sprint

True or False: The Product Owner should be able to explain what the team should be able to do by the end of the sprint during Sprint Planning.

  • True
  • False

True

Sprint Planning involves which of the following items? (Multiple Select)

  • The team planning out their entire work activities for the Sprint.
  • The Scrum Master reviewing what went well and what could be improved from last Sprint.
  • The Product Owner presenting the priorities and the team discussing how to best achieve them.
  • The Product Owner discussing the item at the top of the product backlog.

The team planning out their entire work activities for the Sprint, The Product Owner presenting the priorities and the team discussing how to best achieve them

The maximum recommended duration for Sprint Planning, in a two-week sprint, is usually

  • 1 hour
  • 2 hours
  • 3 hours
  • 4 hours

4 hours

0 0 votes
Article Rating
Subscribe
Notify of
guest
22 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Galina Tišma
3 months ago

This blog on Sprint Planning for the Certified ScrumMaster exam is really helpful. Thanks for sharing!

Jimi Perala
7 months ago

I love how the blog breaks down the roles and responsibilities in a Sprint Planning meeting.

Carl Jensen
3 months ago

Can someone explain the difference between Product Backlog and Sprint Backlog in detail?

Licelima Ferreira
7 months ago

How do you handle a situation where developers disagree on the effort estimation?

Felipe Soler
5 months ago

Nice overview! Helped me get a clearer picture. 😄

Ava Gagné
5 months ago

I found the section on task breakdown extremely useful. 🙏

Francisca Rodríquez
7 months ago

One minor critique: I think the blog could include examples of common pitfalls during Sprint Planning.

Mariël Hamel
4 months ago

Very insightful blog, explained the Sprint Planning process well!

22
0
Would love your thoughts, please comment.x
()
x